Methodology — v0.1
How we measure a megawatt.
Every figure Joule publishes comes from public market data and a reproducible model. This page is the complete method — so your team can check our numbers before you ever talk to us.
M—01Reference site
All figures refer to a standardized 10 MW AI datacenter (IT capacity, meter side scaled by PUE 1.25):
| Load class | IT capacity | Utilization | Flexibility |
|---|---|---|---|
| Inference — tier 1 (real-time) | 4.75 MW | diurnal profile | none |
| Inference — tier 2 (async / batch) | 0.25 MW | diurnal | minutes-scale |
| Training | 4.0 MW | 75% target | hours-to-days deferrable |
| Base (cooling, network, storage) | 1.0 MW | constant | none |
Training energy is conserved: 72 MWh per day must be delivered within each 24-hour window — flexibility means when, never whether.
M—02Data sources
- Day-ahead spot prices — EPEX (DE-LU, FR) via the public energy-charts.info API; SEMOpx for the Irish SEM. Uniform hourly resolution throughout.
- Ancillary capacity prices — regelleistung.net (German TSO joint platform), twelve months of weekly tenders, FCR and aFRR.
- Capacity market parameters — SEM Committee auction information packs and decision papers (CRM T-4 2028/29, 2029/30).
M—03Dispatch model
Two scheduling strategies compete on identical data:
naive: fill the fixed night window 22:00–06:00 first — the heuristic operators actually use
Capture rate = realized savings ÷ oracle savings, against a flat-schedule baseline. All accounting is energy-conserving at uniform hourly resolution.
M—04Results
| Market | Oracle savings / yr | Share of power bill | Naive capture |
|---|---|---|---|
| Ireland (SEM) | €815k | 9.6% | ~33%¹ |
| Germany (DE-LU) | €938k – €1.12M | 12–14% | ~51% |
| France (FR) | €740k – €0.99M | 15–17% | ~46% |
The naive baseline's annual figure conceals a structural split: it captures 85–97% in winter (wind makes nights cheap) but only 20–35% in summer (solar makes midday cheap). The optimizer's edge concentrates exactly where value is most volatile.
Stacking the dispatchable share of these layers on top of arbitrage brings the total annual value pool for the reference site to ≈ €1.0–1.4M, depending on market and registered flexible capacity (3.6 MW of 10 MW in this configuration). Site-specific figures are computed, not extrapolated, in every audit.
M—05Limitations
- Oracle is an upper bound; production systems are gated at ≥60% capture.
- Hourly resolution understates intraday optionality; telemetry-grade modeling ships with audits.
- Irish spot series ends May 2026 pending ENTSO-E access; figures marked ¹ reflect that window.
- No storage assumed. Storage-backed configurations unlock FCR symmetry and are assessed per site.
Questions, replication attempts, disputes: hello@joule-os.com. We answer all three.